Callide Power Station is an electricity generator at Mount Murchison, Shire of Banana, Queensland, Australia. It is coal powered with eight steam turbines with a combined generation capacity of 1,720 megawatts (MW) of electricity. Callide A was commissioned in 1965, refurbished in 1998 and decommissioned in 2015/16.[2] As of 2018, generation capacity was 1510 MW.[2]
Callide Power Station | |
---|---|
Country | Australia |
Location | 1092 Biloela Callide Road, Mount Murchison, Shire of Banana, Queensland |
Coordinates | 24°20′42″S 150°37′11″E / 24.3450°S 150.6196°E |
Status | Offline November 2022 |
Commission date | 1965 |
Construction cost | $28.7 million |
Owners | CS Energy (50%), Intergen (50%)[1] |
Thermal power station | |
Primary fuel | Coal |
Turbine technology | Steam turbines |
Cooling source | Fresh |
Power generation | |
Units operational | 8 |
Nameplate capacity | 1,720 MW |
The coal for Callide comes from the nearby Callide Coalfields and water from the Awoonga dam and Stag Creek Pipeline.[3]
An explosion and fire at the Callide C power plant in late May 2021 caused a significant power outage that affected over 375,000 premises and raised electricity prices for weeks afterwards.
November 2022 all four units at the coal-fired Callide Power Station were not operating after a structural failure at the cooling plant brought the C3 unit offline, and later on the B2 unit tripped during scheduled testing, followed by the last unit, B1, also tripping.[4][5]
CS Energy owns 100 per cent of Callide A and Callide B, and owns Callide C in a 50/50 joint venture with IG Power.
Callide A
editAt the end of 1962 approval was granted for a new power station near Biloela.[6] Work commenced at the site in February 1963. The design of the plant based around separate generating units and a control room was a first for Queensland.[6] It was also the first power station in Queensland to use dry cooling towers.[6]
It had four 30 MW steam turbines, the first of which was operating by June 1965. From its commissioning a drought meant water restrictions at the station reduced output.[6] The second set was expected to be operating by May 1966, but was lost at sea while being transported from England.[6] A replacement unit arrived in June 1967. The third set was operating in October 1967 and the fourth in May 1969.[6] The total cost of the project was A$28.7 million.[6]
Callide A has been in storage since 2001, except for Unit 4 which was being used for the Callide Oxyfuel project.[7] The Callide Oxyfuel project was decommissioned in 2015/16 after demonstrating carbon capture technology for two years.[2]
Callide B
editFollowing on from an aggressive construction program at Tarong Power Station, Callide B was commissioned in 1988 with two 350 MW steam turbines. The Hitachi machines are almost identical to those in Tarong and Stanwell.
In October 2019, Federal Energy Minister Angus Taylor announced that Callide B's originally planned 2038-39 closure was being brought forward to 2028.[8]
Callide C
editThe Callide Power Plant (a.k.a. Callide C) was commissioned in 2001 with two 405 MW advanced cycle steam turbines.[9] Callide C uses a more efficient "supercritical" boiler technology to burn coal to generate electricity.[10] It was built to operate to 2050.[11]
Carbon Monitoring for Action estimates this power station emits 5.73 million tonnes of greenhouse gases each year as a result of burning coal.[12] The Australian Government introduced a Carbon Pollution Reduction Scheme in 2011 to help combat climate change, intended to reduce emissions from power stations. The scheme was replaced in 2014 by a 'direct action' program. The National Pollutant Inventory provides details of other pollutant emissions, but, as at 23 November 2008, not CO2.[13]
On 25 May 2021, an explosion and subsequent fire at Callide C caused a significant power outage (including Callide B and parts of Stanwell and Gladstone power stations)[14] that affected over 375,000 premises,[15][16][17] and caused increased power prices for weeks.[18] The hydrogen-filled generator had a catastrophic failure, resulting in significant damage. Despite speculation that the plant would close, Callide C3 was repaired at an estimated cost of $200M and reopened in April 2024.[19]
As of 25 June 2024, Callide C4 turbine had not returned to service. It was destroyed in May 2021. As of February 2024, insurance carriers had refused to pay the $300M claimed by CS Energy.[20] In June 2024, news reporter Josh Bavas joined Gary Hardgrave on 4BC radio to discuss maintenance failures which led to the catastrophic Callide explosion.[21] However, a February 2024 technical report found that the explosion was caused by a voltage collapse during installation of a new battery charger.[22] In addition, a June 2024 commissioned report into the explosion by a forensic engineer found that a lack of "effective process safety practices" contributed to the incident.[23]
Callide Unit C4 was returned to service on 30 August 2024[24].
A 200 MW solar park with 200 MW / 800 MWh battery is planned for the site.[25]
See also
editReferences
edit- ^ "Callide Power Station". Retrieved 24 March 2022.
- ^ a b c "Callide Power Station". Archived from the original on 2 October 2018. Retrieved 2 October 2018.
- ^ InterGen Archived 2008-08-05 at the Wayback Machine page on Callide. Retrieved 2008-05-18
- ^ Hines, Jasmine; Culliver, Paul (4 November 2022). "Callide Power Station in central Queensland completely offline". ABC News. Australian Broadcasting Corporation. Retrieved 4 November 2022.
- ^ Loftus, Tobi; Culliver, Paul (1 November 2022). "'Structural failure' at Callide Power Station near Biloela leaves unit offline". ABC News. Australian Broadcasting Corporation. Retrieved 4 November 2022.
- ^ a b c d e f g Dunn, Col (1985). The History of Electricity in Queensland. Bundaberg: Col Dunn. pp. 136–139. ISBN 0-9589229-0-X.
- ^ Spero, Chris; Yamada, Toshihiko; Nelson, Peter; Morrison, Tony; Bourhy-Weber, Claire. "Callide Oxyfuel Project – Combustion and Environmental Performance" (PDF). www.eventspro.net. 3rd Oxyfuel Combustion Conference. Retrieved 5 May 2017.[permanent dead link]
- ^ "Qld to close coal-fired power station a decade early". Australian Financial Review. 6 October 2019. Archived from the original on 10 March 2021. Retrieved 3 April 2021.
- ^ InterGen & CS Energy Open US$800 MLN Australian Power Project. AsiaPulse News. 05-JUL-2001 Retrieved 2008-05-18
- ^ Australia joins the supercritical ranks: although a country with a coal-based power industry, Australia has taken up supercritical technologies surprisingly late. However, once started there seems to be no stopping. Here we look at a series of new supercritical developments that have been commissioned in the coal country of Queensland. Modern Power Systems 01-APR-2005 Retrieved 2008-05-18
- ^ Carabott, Mike (2 June 2021). "Callide C power station to be repaired for $200 million". Leading Edge Energy. Archived from the original on 11 July 2021. Retrieved 22 January 2022.
- ^ Callide C Archived 26 July 2011 at the Wayback Machine. Carbon Monitoring for Action. Retrieved on 23 November 2008
- ^ "National Pollutant Inventory". www.npi.gov.au. Archived from the original on 20 May 2017. Retrieved 5 May 2017.
- ^ Parkinson, Giles (3 June 2021). "Queensland coal generators tripped off like dominoes after Callide explosion". RenewEconomy. Archived from the original on 14 August 2021.
- ^ "Queensland power outage leaves hundreds of thousands in dark". 25 May 2021. Archived from the original on 25 May 2021. Retrieved 25 May 2021.
- ^ CS Energy [@CSEnergyQld] (25 May 2021). "CS Energy has immediately acted following an incident at Callide Power Station near Biloela in Central Queensland today" (Tweet) – via Twitter.
- ^ "Archived copy". Facebook. Archived from the original on 22 January 2022. Retrieved 25 May 2021.
{{cite web}}
: CS1 maint: archived copy as title (link) - ^ Leitch, David (7 June 2021). "Price explosion: Gas producers clean up as sun goes down in post Callide world". RenewEconomy. Archived from the original on 7 June 2021.
- ^ Hill, Joshua (2 April 2024). "Callide coal unit returns to service after multiple delays with new cooling tower". Renew Economy. Retrieved 29 May 2024.
- ^ "$300m insurance claim goes boom after power station explosion". Australian Financial Review. 14 February 2024. Retrieved 9 July 2024.
- ^ "From stuff up to cover-up: Shocking extent of the government's handling of Callide revealed - 4BC Drive with Peter Gleeson". omny.fm. 25 June 2024. Retrieved 9 July 2024.
- ^ Weik, Juan (14 February 2024). "Australian coal plant blast cause 'complex': CS Energy". www.argusmedia.com. Retrieved 9 July 2024.
- ^ "Damning report into catastrophic power station explosion finds operator failed to implement 'effective safety practices'". ABC News. 25 June 2024. Retrieved 9 July 2024.
- ^ McArdle, Paul (30 August 2024). "Return to service commences for Callide C4 on Friday 30th August 2024 (after 1193 days offline)!". WattClarity. Retrieved 14 October 2024.
- ^ "Solar farm, huge battery and up to 1,000 sheep get federal green tick for next to coal plant". RenewEconomy. 12 July 2024.
External links
edit- CS Energy page on Callide
- Callide Coal-Fired Power Stations, Queensland, Australia