Soyuz LOK Soyuz LOK lunar orbiter. Credit: © Mark Wade |
Launched: February-March 1970. Number crew: 3 .
These would have been 15 to 16 day missions to demonstrate both the new SZhO life support system for the L3, to conduct rendezvous and docking operations using the L3's Kontakt system, and to conduct EVA transfer of one cosmonaut.
The commission considers plans for the rest of the Soyuz production. Spacecraft s/n 14, 15, and 16 are to fly in August 1969, 17 and 18 in November 1969, and 19 and 20 in February-March 1970. Crews selected for the August flights are: for spacecraft 14, Shonin and Kubasov; for 15, Filipchenko, Volkov, and Gorbatko; for 16, Nikolayev and Sevastyanov. Back-ups will be Kuklin, Grechko, and Kolodin. All of the spacecraft will fly 4 to 5 day missions. Spacecraft 15 and 16 will dock and remain together 2 or 3 days to form an 'orbital station'. Experiments planned for the flight are:
Spacecraft 17 through 20 will fly 15 to 16 day missions to demonstrate the new SZhO life support system for the L3, and conduct rendezvous and docking operations using the L3's Kontakt system. Additional Details: here....
However the board makes a big fuss over Kamanin having trained only four back-up cosmonauts to support eight prime-crew cosmonauts. A follow-up meeting is held with Smirnov and Afanasyev at 19:15, where Kamanin's training is denounced as a big failure. Nevertheless at 22:00 the word comes from the Kremlin to proceed with the missions. Kamanin points out that simultaneously with this mission he had cosmonauts in training for Soyuz s/n 17, 18, 19, 20 (Kontakt missions) and L1 circumlunar fights. Kuznetsov, Beregovoi, and several other cosmonauts are also enraged with Kamanin for bumping Nikolyaev from the Soyuz 8 crew. Kamanin maintains that in the circumstances he only had enough training resources for 8 prime + 4 back-up crew, especially for a mission scenario that would not be flown again in the future.
It was originally planned to fly two Soyuz spacecraft in August-September 1970, but at the end of December it was ordered that this be changed to a single 20 day flight in April 1970. Kamanin was given only two days to put together a training programme that had to prepare the cosmonauts for flight by 20 March. The State Commission meets and decides to move the Soyuz 9 flight to May, even though Kamanin says he can support the April schedule. It is the scientific institutes who say they cannot finish development of their experiments - even to meet the May schedule. Kamanin blames such chaos on Smirnov, Serbin, and Ustinov.
Meeting with Mishin. It is clear that he wanted to continue with the original plan for a dual Soyuz flight in August. It was Afanasyev and Kerimov who were pushing for a single long-duration flight in May. There is no action by the Ministry of Defence to provide rational decision making in regard to manned spaceflight.
A meeting is held on the DOS project. The Central Committee and Soviet Ministers have directed that two DOS space stations be completed by the end of 1970. TsNIIMASH thinks this is impossible - the task can be accomplished in no less than 18 to 24 months. Mishin insists it can be done in ten months, as directed. Kamanin believes he won't even have it ready by the second half of 1971. It took five to seven years to just bring the Almaz, Soyuz VI, and L1 to flight status. This DOS will stop work on all other projects. Mishin still wants to fly two Soyuz spacecraft to test Bogomolov's Kontakt docking system for the L3.